Brisbane’s new runway was not just a runway project. It included doubling Brisbane Airport's airfield and all associated facilities.
Construction included:
Work to prepare the site began in 2012. The final major stages of construction to build the runway, taxiways and airfield got underway in 2017 as the ground transformation works had performed according to plan. Construction was completed in mid-2020, ready for the runway to official open on Sunday 12 July 2020.
For more details about the various elements of construction, including pavements, lighting, landscaping and the Dryandra Road underpass, visit BNE's Youtube channel.